Asbestos removed from a 1950s house before a factory-built home takes its place
Example project
- Home
- 1950s one-story in Blaine with a full basement and an old furnace
- Original request
- Demolish the house and put a factory-built home on a new foundation
- Testing
- An MDH-certified inspector surveyed the whole house ahead of the permit application
- Found
- Positive: ceiling texture in the living room and bedrooms, basement floor tile, kitchen sheet vinyl and duct wrap at the furnace
- Clear
- Plaster walls, roofing and wood siding: no asbestos found
- Timeline
- Survey; MDH notice five days ahead; four days of removal; demolition two or more days after the last bag
- Cost
- $11,200
In this example, a Blaine couple has ordered a factory-built home for the lot their 1950s house sits on. The old house and its basement must be gone before the new foundation goes in, which means a city demolition permit.